TM 11-5860-200-12
Table 3-1. Inspection Requirements
STEP
INSTRUCTIONS
CORRECTIVE ACTION
1
2
Check received item against
Report all discrepancies using
packing slip to see if shipment
instructions in TM 38-750.
is complete.
3
Inspect equipment for damage
If equipment has been damaged
incurred during shipment.
due to packaging, report the
damage on SF 364, Report of
Packaging and Handling
Deficiencies.
4
Inspect chassis and covers for
Refer to following paragraphs for
condition of paint finish and
paint touch-up:
panel markings. All surfaces
should be in good condition.
Control panel markings should
be legible.
5
Inspect control panel spring
Refer to higher category of
lock fasteners and connectors.
maintenance.
They should be in good
condition.
6
Inspect connector pins. All
Refer to higher category of
connectors must be tightly
maintenance.
mounted. Connectors should
have no bent, broken, or
missing pins. No foreign
material should be in
connectors.
7
Operate all control panel
Refer to higher category of
controls through their
maintenance.
positions. All controls should
operate smoothly with no
binding.
3-2